Planning permission and prior declaration: submitting your application online

8 October 2026 · 5 min read · By the Aldeak team

Stone house façade under scaffolding during refacing works
Stone façade refacing, Gironde. Completed by Aldeak.

Replacing windows, refacing a façade, building an extension: many works require planning permission. The good news is that the application can now be submitted online, without going to the town hall.

Prior declaration or building permit?

The thresholds depend on the floor area created and on the zone of the local urban plan. Above 150 m² of total floor area after the works, an architect is compulsory for a building permit.

Submitting online

Since 1st January 2022, every municipality must be able to receive planning applications electronically. The French public service offers an online assistant that helps you choose the right form, put the application together and then send it to the municipality. You can then follow the progress of the review without travelling.

Once it has been sent, you receive an electronic acknowledgement of registration, followed by a receipt showing the application number and the date from which the processing period is calculated. Requests for documents and the decision then arrive by the same route.

Keep the receipt safe: it is what tells you, where relevant, when tacit approval has been obtained.

The documents in the application

For a detached house, the prior declaration uses cerfa form no. 13703 and the building permit cerfa form no. 13406. The application generally includes:

With a digital application, each document is a file: legible plans, drawn to scale and clearly named, avoid a great deal of back and forth.

The timescales to allow for

As a general rule, a prior declaration is processed in one month and a building permit for a detached house in two months. These periods are extended in a protected area, when the opinion of the Architecte des Bâtiments de France (the state heritage architect) is required. They only run from the date the application is complete: a missing document restarts the clock.

1 monthprocessing time as a general rule for a prior declaration
2 monthsfor a building permit for a detached house
3 yearsvalidity of the permission, which can be extended twice by one year

If the application is incomplete, the town hall has one month to request the missing documents, and the applicant has three months to provide them. If the town hall has not replied by the end of the processing period, permission is in principle granted tacitly, with some exceptions (notably in protected areas). Once obtained, it is valid for three years and can be extended twice by one year, on a request made at least two months before it expires.

An example timetable

Worked example: windows and façade refacing on a stone house

Take, by way of example, the replacement of the windows and the refacing of a stone house outside a protected area. The prior declaration is complete: the town hall has one month. The permission is displayed on the site on the day it is granted. The two months during which third parties may appeal are the ideal time to order the joinery, which often takes several weeks to manufacture.

Application submitted onlineearly March
Processing (1 month): approval and displayearly April
End of the third-party appeal period (2 months)early June
Works start, without riskJune

In a protected area, you would need to allow one more month for processing.

After approval

  1. Display the permission on the site, visible from the street, for the whole duration of the works.
  2. Respect the third-party appeal period (two months from the display) before starting any major works.
  3. Declare the start of works for a building permit, then their completion and compliance.

After the declaration of completion, the town hall in principle has three months to challenge the compliance of the works, or five months in some cases (notably in protected areas). The development tax, if the project creates floor area, must be declared within 90 days of completion.

Mistakes to avoid

How we help

On our renovation and extension projects, we prepare the plans, photographs and statements for the application with you, and we schedule the works around the processing periods.

Sources : Code de l’urbanisme, article L. 423-3 (dépôt des demandes par voie électronique depuis le 1er janvier 2022) · Code de l’urbanisme, articles R. 423-23 (délais d’instruction) et R. 600-2 (délai de recours des tiers) · Code de l’urbanisme, articles R. 423-38 et R. 423-39 (pièces manquantes : un mois pour les réclamer, trois mois pour les fournir) · Code de l’urbanisme, articles R. 424-17 et R. 424-21 (validité de trois ans et prorogation) · Code de l’urbanisme, article R. 462-6 (délai de contestation de la conformité des travaux) · Code de l’urbanisme, article R. 431-2 (recours à un architecte) · service-public.gouv.fr, permis de construire · service-public.fr

Frequently asked questions

Can a building permit be submitted online?

Yes, every municipality has had to accept planning applications electronically since 1 January 2022.

Do I need permission to replace my windows?

Yes, if the external appearance changes (material, colour, design): a prior declaration is then required.

When can the works start?

Once the permission has been obtained and displayed; it is wise to wait until the end of the two-month third-party appeal period.

How long does a permission remain valid?

Three years, which can be extended twice by one year, on a request made at least two months before it expires.

What happens if the town hall does not reply?

In principle, permission is granted tacitly at the end of the processing period, with some exceptions, notably in protected areas.

Which form should be used for a detached house?

Cerfa form no. 13703 for a prior declaration and cerfa form no. 13406 for a building permit. The French public service's online assistant helps you choose.

Can I still submit a paper application?

Yes, private individuals can still submit their application at the town hall or send it by recorded delivery.